Air Liquide Botany

APS Engineering tested and commissioned a 3.3 kV switchboard panel fitted with an ABB REM615 motor protection relay at Air Liquide's Botany facility. The work gave the site a verified, reliable protection scheme for its high-voltage motor drives.

Marine & PortsBanksmeadow, NSW2022
Marine & Ports
Sector
Banksmeadow, NSW
Location
Project delivery
Duration
2022
Year
Project overview

The engagement

Air Liquide's Botany facility produces and supplies industrial gases that customers across New South Wales depend on around the clock. As part of switchboard works at the site, APS Engineering was engaged to test and commission a 3.3 kV switchboard panel protected by an ABB REM615 motor protection relay. Our team verified the relay settings, protection functions, and associated control circuits before energising the panel and returning it to service.

The challenge

What the site demanded

Industrial gas production runs continuously, and large high-voltage motors are central to the process. An incorrectly set or untested motor protection relay can lead to nuisance tripping and lost production or, worse, leave a motor unprotected against faults, overloads and stalling. Air Liquide needed an independent, experienced testing team to prove the new 3.3 kV panel and its protection before energisation, within a tight outage window.

Scope of work

What APS delivered

  • Review of protection settings, schematics and wiring diagrams
  • Configuration checks and settings upload to the ABB REM615 relay
  • Secondary injection testing of motor protection functions (e.g. thermal overload, overcurrent, earth fault, unbalance, stall/locked rotor)
  • CT circuit checks, including ratio, polarity and insulation resistance
  • Control, interlock, trip and alarm circuit functional testing
  • Pre-energisation checks and support during energisation
  • Commissioning test reports
Technical solution

How the solution was engineered

APS began with a detailed review of the protection settings and drawings, so that any issues were found and resolved before testing started. Using secondary injection test equipment, our engineers tested each enabled motor protection element of the REM615 and confirmed that pickup values and operating times matched the approved settings. CT circuits were checked for correct ratio and polarity, and every trip, interlock and alarm path was functionally tested through to the circuit breaker. This systematic approach meant the panel was proven as a complete system, not just as individual components, before it went live.

Outcome

How it landed

The 3.3 kV switchboard panel was successfully commissioned and returned to service within the planned outage. Air Liquide now has a fully verified motor protection scheme that protects critical plant while avoiding unnecessary trips. Complete test documentation was handed over to support the site's maintenance and compliance records.

Under the hood

Services applied, equipment used, standards engineered against

A traceable record of which APS services were on this engagement, which calibrated kit it ran on, and which codes the work was witnessed against.

Equipment used

  • ABB REM615 Motor Protection Relay
  • 3.3 kV HV switchboard panel
  • Secondary injection test set (confirm model, e.g. Omicron CMC 356)

Standards

    More from the portfolio

    Other recent work

    Adjacent engagements across the same disciplines and sectors

    Schneider Electric and Reyrolle Argus protection relay maintenance testing at a Melbourne logistics facility

    Marine & Ports Melbourne, Victoria, Australia 2027

    DP World Logistics – Protection Relay Maintenance & Operational Testing

    APS Engineering undertook maintenance and operational testing of Schneider Electric and Reyrolle Argus protection relays at a Melbourne logistics facility. The work focused on assessing relay operation as part of the site’s electrical maintenance activities, supporting informed decisions about protection-system reliability and ongoing asset maintenance.

    • Operations and Maintenance
    • Testing and Commissioning of Power Systems
    View Project
    Aerial view of an illuminated mine at night

    Marine & Ports Narrabri, NSW 2020

    22 kV Substation Testing & Commissioning

    APS Engineering, working with CJP, tested and commissioned 22 kV electrical equipment at Cargill's Narrabri facility. The project delivered a proven, reliable HV supply to support the site's processing operations.

    • Equipment Rentals
    • Primary Design and Engineering
    • SCADA and Automation
    View Project
    Let's talk

    Have an asset to test, commission or audit?

    Send a sketch, an SLD or just a paragraph. Our engineering team will reply within one business day with a scope, fee and mobilisation plan.