How we approach testing and commissioning of power systems

We test primary plant and secondary systems against approved drawings, settings and specifications. This includes insulation resistance, winding resistance, ratio and vector group tests on transformers, timing and contact resistance tests on circuit breakers, CT and VT verification, and primary and secondary injection testing of protection relays.