Brisbane Airport

Commissioning of two Schneider Electric P5U20 protection relays across MSB-1 and MSB-2 at Brisbane Airport, including associated current transformer (CT) testing to support reliable electrical protection and system operation.

AirportsBrisbane2025
Aviation & Critical Infrastructure
Sector
Brisbane
Location
3 Weeks
Duration
2025
Year
Project overview

The engagement

Australian Power Systems Services (APS) undertook protection relay commissioning and current transformer testing at Brisbane Airport. The scope involved two Schneider Electric P5U20 protection relays installed across Main Switchboards MSB-1 and MSB-2, along with testing of their associated CTs.

The works focused on verifying the protection equipment and supporting the reliability and operational readiness of the airport's electrical distribution infrastructure.

The challenge

What the site demanded

The project's electrical protection systems required commissioning and verification to ensure the installed protection relays and associated current transformers were suitable for operation. Accurate current measurement and dependable protection performance were essential for supporting the reliability of the main switchboards.

Scope of work

What APS delivered

Commissioning of two Schneider Electric P5U20 protection relays installed in MSB-1 and MSB-2. Testing and verification of the associated current transformers (CTs). Verification of protection relay configurations and settings as part of the commissioning process. Documentation of commissioning activities and test results.

Technical solution

How the solution was engineered

APS carried out the commissioning of two Schneider Electric P5U20 protection relays installed in MSB-1 and MSB-2 at Brisbane Airport. The works included protection relay configuration and verification, along with testing of the associated current transformers (CTs) to confirm their performance and measurement accuracy. The commissioning activities focused on ensuring the protection relays and CTs were correctly integrated into the electrical distribution system, supporting reliable fault detection, equipment protection and safe operation of the main switchboards.

Outcome

How it landed

APS completed the assigned protection relay commissioning and CT testing activities across MSB-1 and MSB-2. The works contributed to verifying the installed protection equipment and supporting the operational readiness and reliability of the electrical distribution system.

Under the hood

Services applied, equipment used, standards engineered against

A traceable record of which APS services were on this engagement, which calibrated kit it ran on, and which codes the work was witnessed against.

More from the portfolio

Other recent work

Adjacent engagements across the same disciplines and sectors

Hyperscale data centre power room

Transport Pascoe Vale, VIC 2023

Yarra Trams Substation Testing & Commissioning

Working with CJP, APS Engineering tested and commissioned electrical and protection equipment at a Yarra Trams site in Pascoe Vale. The work supports a reliable power supply for Melbourne's tram network.

  • Equipment Rentals
  • Primary Design and Engineering
  • Testing and Commissioning of Power Systems
View Project
Schneider Electric and Reyrolle Argus protection relay maintenance testing at a Melbourne logistics facility

Marine & Ports Melbourne, Victoria, Australia 2027

DP World Logistics – Protection Relay Maintenance & Operational Testing

APS Engineering undertook maintenance and operational testing of Schneider Electric and Reyrolle Argus protection relays at a Melbourne logistics facility. The work focused on assessing relay operation as part of the site’s electrical maintenance activities, supporting informed decisions about protection-system reliability and ongoing asset maintenance.

  • Operations and Maintenance
  • Testing and Commissioning of Power Systems
View Project
APS Engineering specialists testing 11 kV switchgear at the Lihir gold mine, Papua New Guinea

Mining Lihir Island, New Ireland Province, PNG 2026

Lihir Gold Mine

APS Engineering deployed 21 specialists to the Lihir gold mine in Papua New Guinea to deliver an 11 kV switchgear upgrade, plant-wide maintenance and testing works, an engineering review, and site acceptance testing. We worked with Voltex to deliver the works.

  • Power Asset Inspections
  • Equipment Rentals
  • Primary Design and Engineering
View Project
Let's talk

Have an asset to test, commission or audit?

Send a sketch, an SLD or just a paragraph. Our engineering team will reply within one business day with a scope, fee and mobilisation plan.