APS mobilised 21 specialists, including protection engineers and testing technicians, so the full scope could be delivered in parallel within the available shutdown windows. Before works began, our engineers carried out an engineering review of the protection design, settings and drawings, so that issues could be found and resolved early. Teams then carried out the 11 kV switchgear upgrade and completed site acceptance testing to prove that the new equipment and its protection worked correctly before return to service. At the same time, APS crews delivered plant-wide maintenance testing: they tested protection relays against approved settings and checked CTs, circuit breakers and trip circuits to confirm the complete protection chain worked as designed. We recorded defects and discrepancies clearly and worked with the client to prioritise corrective action. The team carried out all work under the mine's permit-to-work and isolation procedures.