Stubbo Solar Farm Substation – Protection & SCADA Testing and Commissioning

APS Engineering, working with Zinfra on behalf of Transgrid, delivered an engineering review, IEC 61850 SCADA signal testing, and full protection factory acceptance testing (FAT) and site acceptance testing (SAT) for the Stubbo Solar Farm Substation. testing and commissioning of protection systems in dubbo, New South Wales. Our work helped bring a major utility-scale solar project online.

RenewablesCentral West, Dubbo, NSW2024
Renewables
Sector
Central West, Dubbo, NSW
Location
Project delivery
Duration
2024
Year
Project overview

The engagement

Stubbo Solar Farm is a utility-scale solar project in the Central-West region of New South Wales, supplying renewable generation to the National Electricity Market. Zinfra, delivering substation works for Transgrid, engaged APS Engineering to provide specialist protection and SCADA testing for the Stubbo Solar Farm Substation. Over nine months, a team of six APS engineers carried out the engineering review, IEC 61850 SCADA signal testing, and factory acceptance testing (FAT) and site acceptance testing (SAT) of the entire substation protection system. Our work ensured every protection and control function was proven before the substation was energised and connected to the transmission network.

The challenge

What the site demanded

A substation connecting a utility-scale solar farm to Transgrid's transmission network must meet strict performance, protection and connection requirements. The project used a modern IEC 61850 digital substation design, where protection, control and SCADA functions rely on networked communications rather than traditional hard-wired signals. Every signal, interlock and protection function had to be verified, both in the factory and on site, before energisation. Zinfra needed an experienced, well-resourced protection team that could carry out this work rigorously and keep pace with a demanding construction and commissioning program at a regional site.

Scope of work

What APS delivered

  • Engineering review of protection settings and design documentation
  • IEC 61850 SCADA signal testing and verification
  • Secondary injection testing of substation protection relays
  • CT and VT testing
  • Trip, intertrip, interlock and alarm functional testing
  • Energisation and grid connection support
  • Commissioning documentation
  • Test reports and commissioning documentation to Transgrid requirements
Technical solution

How the solution was engineered

APS deployed a dedicated team of six engineers for nine months, covering the project from design review through to energisation. We started with a detailed engineering review of the protection design and settings, finding and resolving issues early, before they could affect testing on site. During FAT, our engineers tested the protection and control panels in the factory, proving relay functions and IEC 61850 communications before the panels shipped. On site, we carried out full SAT of the substation protection system: we tested every protection relay against approved settings, verified instrument transformers, and proved trip, intertrip and interlock schemes end to end. We also tested each IEC 61850 SCADA signal from source to control system, so that the network operator would receive accurate and reliable data. We produced comprehensive documentation to Transgrid's standards to support energisation and network connection.

Outcome

How it landed

APS completed the engineering review, FAT, SAT and SCADA testing, and the Stubbo Solar Farm Substation was successfully energised and connected to Transgrid's network. Proving the protection and IEC 61850 systems at both factory and site stages reduced commissioning risk and supported a smooth handover. The project shows APS's ability to resource and deliver complex digital substation commissioning for major transmission projects. It also strengthened our relationship with Zinfra and Transgrid.

Under the hood

Services applied, equipment used, standards engineered against

A traceable record of which APS services were on this engagement, which calibrated kit it ran on, and which codes the work was witnessed against.

Equipment used

  • Substation HV switchgear
  • Protection relays (confirm makes/models)
  • Secondary injection test set (confirm model, e.g. Omicron CMC 356)

Standards

    More from the portfolio

    Other recent work

    Adjacent engagements across the same disciplines and sectors

    Battery energy storage system at Broadsound, Queensland, tested and commissioned by APS Engineering

    Renewables Broadsound, QLD 2026

    Broadsound BESS – Testing & Commissioning

    APS Engineering, working with JTMEC, delivered testing and commissioning for a battery energy storage system (BESS) at Broadsound in Central Queensland for Yurika. Our work helps strengthen Queensland's grid with new energy storage.

    • SCADA and Automation
    • Digital Substations
    • Testing and Commissioning of Power Systems
    View Project
    MREH

    Renewables Plumpton, VIC 2024

    Melbourne Renewable Energy Hub (MREH) – Testing & Commissioning

    APS Engineering supported Samsung with testing and commissioning at the Melbourne Renewable Energy Hub in Plumpton, one of Australia's largest battery energy storage projects. Our work helped bring critical grid-scale storage online for Victoria.

    • SCADA and Automation
    • Operations and Maintenance
    • Digital Substations
    View Project
    APS Engineering specialists testing 11 kV switchgear at the Lihir gold mine, Papua New Guinea

    Mining Lihir Island, New Ireland Province, PNG 2026

    Lihir Gold Mine

    APS Engineering deployed 21 specialists to the Lihir gold mine in Papua New Guinea to deliver an 11 kV switchgear upgrade, plant-wide maintenance and testing works, an engineering review, and site acceptance testing. We worked with Voltex to deliver the works.

    • Power Asset Inspections
    • Equipment Rentals
    • Primary Design and Engineering
    View Project
    Let's talk

    Have an asset to test, commission or audit?

    Send a sketch, an SLD or just a paragraph. Our engineering team will reply within one business day with a scope, fee and mobilisation plan.