25 kV Traction Supply Testing & Commissioning – Cross River Rail

APS Engineering delivered testing and commissioning of 25 kV traction power equipment at Park Road for Queensland Rail as part of the Cross River Rail program. The work helped prepare the traction supply for integration into South East Queensland's rail network.

Marine & PortsPark Road, Brisbane, QLD2023
Marine & Ports
Sector
Park Road, Brisbane, QLD
Location
Project delivery
Duration
2023
Year
Project overview

The engagement

Cross River Rail is one of Queensland's largest infrastructure projects, delivering new rail capacity through the heart of Brisbane. At Park Road, APS Engineering carried out testing and commissioning of 25 kV traction power equipment for Queensland Rail. Our scope covered protection and control verification to make sure the traction supply would operate safely and reliably as part of the wider network.

The challenge

What the site demanded

Rail traction systems carry high fault levels and must meet strict standards for safety and availability. Work at Park Road had to fit around an operational rail corridor, with limited track access windows and close coordination between many project parties. Queensland Rail needed experienced commissioning engineers who understood traction protection and could deliver results within tightly controlled possessions.

Scope of work

What APS delivered

  • Review of traction protection settings and design documentation
  • Secondary injection testing of 25 kV traction protection relays
  • CT and VT testing and verification
  • Trip, intertrip, interlock and alarm functional testing
  • SCADA / control point-to-point checks (as applicable)
  • Commissioning documentation to Queensland Rail requirements
Technical solution

How the solution was engineered

APS planned its testing in detail ahead of each access window so that work on site was focused and efficient. Our engineers tested the traction protection relays against the approved settings and verified the associated instrument transformers, trip circuits and interlocks. Functional testing confirmed that protection and control schemes worked correctly end to end, including signalling to control systems. All activities followed Queensland Rail's safety, access and documentation requirements.

Outcome

How it landed

The 25 kV traction equipment at Park Road was tested and commissioned to Queensland Rail's requirements, supporting the progress of the Cross River Rail program. The client received full, compliant test records, and the project added to APS's growing experience in rail traction power systems.

Under the hood

Services applied, equipment used, standards engineered against

A traceable record of which APS services were on this engagement, which calibrated kit it ran on, and which codes the work was witnessed against.

Equipment used

  • Secondary Injection Test Set (Omicron CMC 356)
  • Primary Injection Test Set (CPC 100)

Standards

    More from the portfolio

    Other recent work

    Adjacent engagements across the same disciplines and sectors

    Schneider Electric and Reyrolle Argus protection relay maintenance testing at a Melbourne logistics facility

    Marine & Ports Melbourne, Victoria, Australia 2027

    DP World Logistics – Protection Relay Maintenance & Operational Testing

    APS Engineering undertook maintenance and operational testing of Schneider Electric and Reyrolle Argus protection relays at a Melbourne logistics facility. The work focused on assessing relay operation as part of the site’s electrical maintenance activities, supporting informed decisions about protection-system reliability and ongoing asset maintenance.

    • Operations and Maintenance
    • Testing and Commissioning of Power Systems
    View Project
    ABB REM615 motor protection relay on a 3.3 kV switchboard panel at Air Liquide Botany, Banksmeadow NSW

    Marine & Ports Banksmeadow, NSW 2022

    Air Liquide Botany

    APS Engineering tested and commissioned a 3.3 kV switchboard panel fitted with an ABB REM615 motor protection relay at Air Liquide's Botany facility. The work gave the site a verified, reliable protection scheme for its high-voltage motor drives.

    • Power Asset Inspections
    • Equipment Rentals
    • Primary Design and Engineering
    View Project
    Aerial view of an illuminated mine at night

    Marine & Ports Narrabri, NSW 2020

    22 kV Substation Testing & Commissioning

    APS Engineering, working with CJP, tested and commissioned 22 kV electrical equipment at Cargill's Narrabri facility. The project delivered a proven, reliable HV supply to support the site's processing operations.

    • Equipment Rentals
    • Primary Design and Engineering
    • SCADA and Automation
    View Project
    Let's talk

    Have an asset to test, commission or audit?

    Send a sketch, an SLD or just a paragraph. Our engineering team will reply within one business day with a scope, fee and mobilisation plan.