NEXTDC Data Centre Testing & Commissioning

APS Engineering, working with Heyday, tested and commissioned high-voltage electrical and protection systems for NEXTDC data centre infrastructure in Sydney. Our work supported the high-availability power systems that data centres demand.

Data CentresSydney, NSW2024
Data Centres
Sector
Sydney, NSW
Location
Project delivery
Duration
2024
Year
Project overview

The engagement

NEXTDC is one of Australia's leading data centre operators, and its facilities must deliver near-continuous uptime to customers. APS Engineering was engaged by Heyday to test and commission electrical and protection systems for NEXTDC data centre projects in Sydney. Our team verified protection schemes and associated equipment to support reliable, resilient power delivery.

The challenge

What the site demanded

Data centres are built around redundancy and uptime, so the electrical system has to perform perfectly from day one. Protection must be correctly coordinated across complex HV and LV networks, including multiple supplies and backup generation. Heyday needed specialist protection engineers who could work to an aggressive construction schedule and meet the demanding standards of a tier-one data centre operator.

Scope of work

What APS delivered

  • Review of protection settings and coordination
  • Secondary injection testing of protection relays
  • CT testing and insulation resistance testing
  • Control, trip, interlock and transfer scheme functional testing
  • Support for integrated systems testing (as applicable)
  • Commissioning documentation to client standards
Technical solution

How the solution was engineered

APS worked closely with Heyday's project team to align testing with the construction and commissioning schedule. Our engineers tested each protection relay against its approved settings and verified the trip, interlock and transfer logic that underpins the facility's redundancy. Detailed documentation was produced to meet the client's quality requirements and support integrated systems testing.

Outcome

How it landed

The protection and electrical systems were commissioned to NEXTDC's standards, supporting the delivery of high-availability data centre capacity in Sydney. The project demonstrated APS's ability to deliver precise, well-documented work in the fast-paced data centre sector.

Under the hood

Services applied, equipment used, standards engineered against

A traceable record of which APS services were on this engagement, which calibrated kit it ran on, and which codes the work was witnessed against.

Equipment used

  • Secondary injection test set (Omicron CMC 356)
  • CPC 100
  • CT Analyser

Standards

    More from the portfolio

    Other recent work

    Adjacent engagements across the same disciplines and sectors

    APS Engineering specialists testing 11 kV switchgear at the Lihir gold mine, Papua New Guinea

    Mining Lihir Island, New Ireland Province, PNG 2026

    Lihir Gold Mine

    APS Engineering deployed 21 specialists to the Lihir gold mine in Papua New Guinea to deliver an 11 kV switchgear upgrade, plant-wide maintenance and testing works, an engineering review, and site acceptance testing. We worked with Voltex to deliver the works.

    • Power Asset Inspections
    • Equipment Rentals
    • Primary Design and Engineering
    View Project
    APS Engineering technician testing an ABB REG615 protection relay on the Yolla A offshore gas platform, Bass Strait

    Oil & Gas Bass Strait, VIC 2021

    BassGas Project – Yolla A Platform

    APS Engineering installed, tested and commissioned an ABB REG615 generator protection relay on Beach Energy's offshore Yolla A Platform in Bass Strait. We delivered a fully tested protection upgrade in a remote, safety-critical setting with minimal disruption to production.

    • Testing and Commissioning of Power Systems
    View Project
    Battery energy storage system at Broadsound, Queensland, tested and commissioned by APS Engineering

    Renewables Broadsound, QLD 2026

    Broadsound BESS – Testing & Commissioning

    APS Engineering, working with JTMEC, delivered testing and commissioning for a battery energy storage system (BESS) at Broadsound in Central Queensland for Yurika. Our work helps strengthen Queensland's grid with new energy storage.

    • SCADA and Automation
    • Digital Substations
    • Testing and Commissioning of Power Systems
    View Project
    Let's talk

    Have an asset to test, commission or audit?

    Send a sketch, an SLD or just a paragraph. Our engineering team will reply within one business day with a scope, fee and mobilisation plan.